High project costs: The Maharashtra Government boasts that overall project costs have been slashed from Rs 9,060 crore to Rs 6,424 crore. But about Rs 1,580 crore of the Rs 2,636-crore cost reduction has been achieved by delinking the re-gassification plant from the original project. The only genuine reduction is Rs 900 crore, voluntarily offered by Enron, following reduction in global prices of power equipment. "This fall in equipment prices is for all power projects and not just Enron," says a Maharashtra State Electricity Board (MSEB) official. These reasons account for over 90 per cent of the cost reduction.