Delhi PWD Shoots Off Notice To L&T Over 'Glaring' Issues In Pragati Maidan Tunnel

The notice by PWD alleged that the project with the passage of time revealed "glaring infirmities that were not only technical in nature but were also design flaws"

Getting your Trinity Audio player ready...
File
The notice, as issued on February 3, asked the company to respond within 15 days | Photo: File
info_icon

Delhi government's Public Works Department (PWD) has issued a notice to Larsen and Toubro over alleged "glaring" issues in the Pragati Maidan tunnel project and directed the company to immediately initiate repair work

While Delhi government demanded a "token amount" of Rs 500 crore from Larsen and Toubro, the firm said that they have made a counterclaim of Rs 500 crore against the PWD.

The notice, issued on February 3, asked the company to respond within 15 days.

Prime Minister Narendra Modi had on June 19, 2022 inaugurated the 1.3-km-long tunnel and five underpasses as part of the Pragati Maidan Integrated Transit Corridor Project that aims to ease connectivity between central Delhi with the eastern parts of the city and the satellite towns of Noida and Ghaziabad.

'Glaring Infirmities'

The tunnel has since then been shut multiple times due to waterlogging during the Delhi floods last year.

The notice by PWD alleged that the project with the passage of time revealed "glaring infirmities that were not only technical in nature but were also design flaws".

"The most glaring as well as alarming issue was the accumulation of water across various locations in the tunnel/underpass.

"This issue, especially during the monsoon season, rendered the entire project non-operational for the general public and ultimately ended up causing far more blockages and congestion along the arterial roads of the entire New Delhi area which defeated the very purpose of this ambitious project," news agency quoted lines from the PWD notice.

No Govt Role In Design, Execution Of Project

The notice also mentioned that the entire design and execution of the project was under the control of L&T and no government agency had any role in it.

The PWD in the notice said the company's "failure to act on the issues being faced by the general public and the resultant public safety hazard, is not only a dereliction of your duty/obligations towards the general public but also contravenes the terms of the agreement.

"Given the documentary records and urgency involved in the redressal process, you are put on notice to respond as to why action should not be instituted against your company within 15 days from the date of receipt of this notice."

In the interim, it directed the company to immediately deposit a "minimum token amount of Rs 500 crore" and initiate repair and rectification work on the locations already identified in the project site.

The PWD in its notice also stated that despite detailed communications and requests from the government agencies, including but not limited to the PWD, seeking urgent and immediate redressal of the issues being faced by the engineers as well as the general public, all the issues have now remained unaddressed for over two months.

The "notable variation" in the actual construction is likely to cause an "irreparable and unprecedented impact" on the underpasses and tunnels which are intended to be utilised by the public for years, the notice stated.

An L&T spokesperson said his company has filed a counter-claim of Rs 500 crore.

"PWD, Delhi, is an esteemed client and we value the long years of association we have enjoyed with them. However, L&T would like to state that a counter-claim of Rs 500 crore has been made by the company against PWD, Delhi," the spokesperson said.